Project Timeline
June 2021
Two community meetings were held in June 2021 to provide information to Middlefield Road businesses about the construction project and to answer any questions. Spanish translation was provided at both meetings.
- Thursday, June 24, 2021 at 10:00am outside at the Middlefield Road Mural Parking lot (Middlefield Road and 2nd Avenue)
- Wednesday, June 30, 2021 at 10:00am via Zoom
May 2021
In May 2021 Construction began on Middlefield Road, including potholing and other work. Postcards were sent out to North Fair Oaks residents and businesses notifying them of the upcoming construction.
![]() |
![]() |
2018-2021
The utility undergrounding work will include placing the overhead utility wires underground and removing the existing utility poles between MacArthur Avenue and Fifth Avenue. Construction of new underground utility system will include utility trenches, generally in the new southbound travel lane of Middlefield Road, and utility vaults or boxes in the new sidewalk.
2017
Sanitary sewer replacement work includes replacing the existing sewer lines between Douglas Avenue and Sixth Avenue as part of the Fair Oaks Sewer Maintenance District’s planned capital improvement work.
2015-2016
The Clinic/Redwood Junction driveway work includes relocation and modification of the driveway, replacement and relocation of railroad track signal and equipment, and installation of a new traffic signal system with railroad preemption (connectivity of traffic signals to the railroad signal system and oncoming trains). Modifications required by the Union Pacific Railroad in connection with the traffic signal work include restricting traffic on Northside Avenue to only allow a right turn from Northside Avenue to Middlefield Road. Accessing Northside Avenue from Middlefield Road or turning left from Northside Avenue to Middlefield Road will not be allowed after the Project is completed.
2012-2014
The Clinic/Redwood Junction driveway work includes relocation and modification of the driveway, replacement and relocation of railroad track signal and equipment, and installation of a new traffic signal system with railroad preemption (connectivity of traffic signals to the railroad signal system and oncoming trains). Modifications required by the Union Pacific Railroad in connection with the traffic signal work include restricting traffic on Northside Avenue to only allow a right turn from Northside Avenue to Middlefield Road. Accessing Northside Avenue from Middlefield Road or turning left from Northside Avenue to Middlefield Road will not be allowed after the Project is completed.
2011
The Clinic/Redwood Junction driveway work includes relocation and modification of the driveway, replacement and relocation of railroad track signal and equipment, and installation of a new traffic signal system with railroad preemption (connectivity of traffic signals to the railroad signal system and oncoming trains). Modifications required by the Union Pacific Railroad in connection with the traffic signal work include restricting traffic on Northside Avenue to only allow a right turn from Northside Avenue to Middlefield Road. Accessing Northside Avenue from Middlefield Road or turning left from Northside Avenue to Middlefield Road will not be allowed after the Project is completed.