All Projects

Project No. SF901; Project File No. E4962

Location

Location: North Fair Oaks Area in Redwood City, CA

About the Project

Project construction will include replacing approximately 5,851 LF of sewer main line, rehabilitating or replacing sewer manholes, slurry sealing and restriping various roads in North Fair Oaks Area. The roads affected by this project will be Nimitz Avenue, Himmel Avenue, Milton Street, Santa Clara Avenue, Hull Avenue, Santiago Avenue, and some portions of Woodside Road.

Public Works Contact

Anthony Lum
Senior Engineer 
alum@smcgov.org
650-363-4100

Contractor

EPS, Inc. dba Express Plumbing

UPDATES
  • March 2022 - Project awarded to EPS, Inc. dba Plumbing Express for a NTE of $2,739,220
  • April 2022 - County executed contract with EPS.  Construction anticipated to begin in June 2022
  • May 2022 - County executed contract with EPS.  Construction anticipated to begin in June 2022
  • June 2022 - Construction commenced early June 2022
  • July 2022 - Contractor continues to work on Woodside Road.
  • August 2022 - Contractor will complete the manhole rehabilitation on Woodside Road and start work on the next street.
  • October 2022 - Contractor starts working on sewer mainline replacement on Santiago Ave.
  • November 2022 -
    • Contractor finishes up sewer replacement on Santiago Ave and moves on to Hull Ave.
    • Construction Status: 35% Complete.
  • December 2022 - Contractor near completion of Hull Ave, and works on MH rehabilitation on Woodside Road.
  • January 2023 - Contractor worked on manhole rehabilitation, and resuming sewer replacement work at Santa Clara Ave.
  • February 2023 - Contractor worked on sewer replacement on Milton Street.
  • March 2023 - Contractor continued sewer replacement work on Milton Street.
  • April 2023 - Contractor's operations on hold due to material delivery delays.
  • May 2023 - Contractor starts sewer replacement work on Himmel Avenue.
  • June 2023 - Contractor continues sewer replacement work on Himmel Ave and Nimitz Ave; and project wide manhole rehabilitation.
  • July 2023 - Contractor continues sewer replacement work on Nimitz Ave; and project wide manhole rehabilitation.
  • August 2023 - Contractor finishes sewer replacement work on Nimitz Ave, replaced all manhole frames and covers, and slurry sealed Santiago Ave, Hull Ave, Santa Clara Ave, Milton Ave, Himmel Ave, and Nimitz Ave.
  • September 2023 - Contractor completes project wide striping work, post construction CCTV and deflection test of the PVC pipe at Himmel Ave and Nimitz Ave. Contractor also completes vacuum. test for all new manholes and starts working on punch list items.
  • October 2023 - Contractor completes punchlist items. The team works on project close-out.
  • November 2023 - Project Close-Out.
Location MapLocation Map Vicinity MapVicinity Map DSC03726August 2023 - Nimitz Ave Slurry Seal DSC03703August 2023 - Himmel Ave Slurry Seal DSC03664August 2023 - Hull Ave Slurry Seal DSC03405August 2023 - Milton St Demo DSC03255August 2023 - Nimitz Ave and W Selby DSC03072August 2023 - Backfill DSC03070August 2023 - Nimitz Ave Excavation DSC04503September 2023 - Vacuum Test DSC04183September 2023 - Deflection Testing DSC03845September 2023 - Legends on Nimitz and Himmel Ave DSC03841September 2023 - Crosswalk on Himmel and Rutherford Ave DSC03831September 2023 - Pavement Marking on Santa Clara Ave DSC03824September 2023 - Pavement Legend on Hull and Santiago Ave DSC03820September 2023 - Pavement Legend at Santiago Ave