Project No. 08SR2; Project File No. E5093000
Location
Near 4901 Stage Road, Pescadero, CA
About the Project
The slip-our repair project will repair the failed embankment and damaged shoulder. The repair will restore the existing bank using a reinforced earth wall.
Public Works Contact
Joshua Rawley
Senior Civil Engineer
jrawley@smcgov.org
650-363-4100
Contractor
Al Matin
Project Manager
SBAY Construction, Inc.
408-490-4390
UPDATES
- January 2023 – Roadway failed due to heavy storms. Preliminary site investigations performed.
- February 2023 - Desktop analysis, development of supporting documents for FEMA, and procurement of geotechnical and drilling firms.
- March 2023 - Coordination with Cal OES/FEMA and monitoring of site.
- May 2023 - Field Meeting with FEMA for site assessment and repair scope development.
- June 2023 - Received and reviewing Geotechnical Investigation Report.
-
July 2023 - Awaiting Contractor to develop proposal for repair work.
-
September 2023 – Entered into contract via our JOC ordering system with SBAY Construction, Inc for the Repair and Reconstruction Work. Work to commence on 9/25/23 and scheduled to 11/17/23 on Monday – Saturday 7:30 AM – 5 PM. Road closed to through traffic. Bicyclist to use alternative route.