All Projects

Project No. 08SR2; Project File No. E5093000

Location

Near 4901 Stage Road, Pescadero, CA

About the Project

The slip-our repair project will repair the failed embankment and damaged shoulder. The repair will restore the existing bank using a reinforced earth wall. 

Public Works Contact

Joshua Rawley
Senior Civil Engineer
jrawley@smcgov.org
650-363-4100

Contractor

Al Matin
Project Manager
SBAY Construction, Inc. 
408-490-4390

UPDATES
  • January 2023 – Roadway failed due to heavy storms. Preliminary site investigations performed.
  • February 2023 - Desktop analysis, development of supporting documents for FEMA, and procurement of geotechnical and drilling firms. 
  • March 2023 - Coordination with Cal OES/FEMA and monitoring of site.
  • May 2023 - Field Meeting with FEMA for site assessment and repair scope development.
  • June 2023 - Received and reviewing Geotechnical Investigation Report.
  • July 2023 - Awaiting Contractor to develop proposal for repair work.

  • September 2023 – Entered into contract via our JOC ordering system with SBAY Construction, Inc for the Repair and Reconstruction Work. Work to commence on 9/25/23 and scheduled to 11/17/23 on Monday – Saturday 7:30 AM – 5 PM. Road closed to through traffic. Bicyclist to use alternative route.

Stage Road #2 - Slip Out