Tunitas Creek December 2025 Construction of EV Charger Footing

December 2025 Construction of EV Charger Footing

Tunitas Creek December 2025 Curb North Entrance Concrete Install

December 2025 Curb North Entrance Concrete Install

Tunitas Creek December 2025 Formwork Curb North Entrance.JPG

December 2025 Formwork Curb North Entrance

Tunitas Creek December 2025 Installing AT&T Conduit to Ranger Station.JPG

December 2025 Installing AT&T Conduit to Ranger Station

Tunitas Creek December 2025 Installing Transformer..JPG

December 2025 Installing Transformer

Tunitas Creek December 2025 Upper Parking Lot Deck Construction.JPG

December 2025 Upper Parking Lot Deck Construction

Tunitas Creek December 2025 Upper Parking Lot Decks and Seatwalls.JPG

December 2025 Upper Parking Lot Decks and Seatwalls

Tunitas Creek December 2025 Upper Parking Lot Installing Seatwall Backs.JPG

December 2025 Upper Parking Lot Installing Seatwall Backs

Tunitas Creek December 2025 Upper Parking Lot Sidewalk Concrete Install.JPG

December 2025 Upper Parking Lot Sidewalk Concrete Install

Tunitas Creek December 2025 Wiring Ranger Station.JPG

December 2025 Wiring Ranger Station

Tunitas Creek October 2025 - Preparing for construction of overlook deck

October 2025 - Preparing for construction of overlook deck

Tunitas Creek October 2025 - Utility pole removal 2

October 2025 - Utility pole removal

Tunitas Creek October 2025 - Utility pole removal

October 2025 - Utility pole removal

Tunitas Creek October 2025 - Wayfinding signage

October 2025 - Wayfinding signage

Tunitas Creek - September 2025 Guardrail Installation ADA Pathway.jpg

September 2025 - Guardrail Installation ADA Pathway

Tunitas Creek - September 2025 Handrail Lighting Work.jpg

September 2025 - Handrail Lighting Work

Tunitas Creek - September 2025 Preparing Handrail for lighting.jpg

September 2025 - Preparing Handrail for lighting

Tunitas Beach August 2025 - Transformer Box at Ranger Shed

August 2025 - Transformer Box at Ranger Shed

Tunitas Beach August 2025 - Signage installation

August 2025 - Signage installation

Tunitas Beach August 2025 - Signage installation 2

August 2025 - Signage installation 2

Tunitas Beach August 2025 - Handrail-Guardrail Installation

August 2025 - Handrail-Guardrail Installation

Tunitas Beach August 2025 - Concrete work for sidewalk at upperparking lot area

August 2025 - Concrete work for sidewalk at upperparking lot area

Tunitas Beach August 2025 - Concrete finishing for sidewalk

August 2025 - Concrete finishing for sidewalk

November 2025 Progress - grading_&_gravel_bags_placed_on_Access_Rd

November 2025 Progress - grading & gravel bags placed on Access Rd

November 2025 Progress - placing_fencing_around_trees_at_LoneStar

November 2025 Progress - Placing Fencing around trees at LoneStar

November 2025 Progress - receiving_plants_at_LoneStar

November 2025 Progress - Receiving plants at LoneStar

November 2025 Progress - deck_work

November 2025 Progress - deck work

November 2025 Progress - grading_at_the_top_level

November 2025 Progress - Grading at the top level

November 2025 Progress - placing_seat_wall_concrete

November 2025 Progress - Placing seat wall concrete

November 2025 Progress - watering_landscaping

November 2025 Progress - Landscaping Irrigation

November 2025 Progress - placing_seat_wall_reinforcing_steel_top_level

November 2025 Progress - Placing seat wall reinforcing steel top level

Main Page

Previous Updates
  • November 2022 - Preparing for demolition phase of the existing single family home
  • December 2022 - JOC Contractor and County negotiate on proposal for demolition work.
  • January 2023
    • Executed JOC Task Order with Olympos Construction for demolition work.
    • Board approves DPW's recommendation to finalize plans and specifications and put the improvements project out to bid.
  • February 2023 - 100% design in progress.
  • March 2023 - House demolition work completed.
  • April 2023 - 100% design complete. Project out to bid on 4/27.
  • May 2023 - Open bids on 5/25. Low responsible bidder is Gordon N. Ball, Inc.
  • June 2023 – Project was awarded to Gordon N. Ball, Inc. by County of San Mateo Board of Supervisors on June 13, 2023.
  • July 2023 - Contract execution. The County and Contractor prepare for forthcoming construction work (Submittal and RFI Review).
  • August 2023 - Contractor mobilizes on 8/29.
  • September 2023 - Contractor works on clearing and grubbing and construction fencing to secure the site.
  • October 2023 - Contractor starts on landslide mitigation area, and clear and grub the south access trail.
  • November 2023 - Contractor importing soil and continues working on landslide mitigation work. Started installing storm drainage from Upper Lot to Mid-Bluff area.
  • December 2023 - Contractor continues working on landslide mitigation work and installing storm drainage from Upper Lot to Mid-Bluff area. Cleared ADA Pathway.
  • January 2024 to March 2024 – Project site is winterized.
  • April 2024 - Contractor commences construction activities.
  • May 2024 - Contractor working on landslide mitigation, storm drain, beach access road, and ADA trail.
  • June 2024 - Contractor is working on the beach access road, finishing installing storm drain facilities, ADA trail and retaining walls, amphitheater area, restroom building pad, and grading the parking lot area.
  • July 2024 - Contractor completed work on the beach access road and retaining walls. Work on grading the ADA trail, amphitheater area, restroom and ranger shed building pads, installing a waterline and electrical conduits, and grading the parking lot area are ongoing.
  • August 2024 - Contractor continued working on installing joint trench, amphitheater area, wood decks, ranger shed foundation, building foundation, and septic tank. Work on CMU walls, parking lots, bioretention areas, pedestrian stairs, wood decks are ongoing.
  • September 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, and installation of bioretention areas, curbs, utility conduits, trail, and grading at the upper parking lot area.

    Temporary traffic control measures are in place along Highway 1 shoulder. Highway 1 work is anticipated to be completed by mid to late September.

  • October 2024 - Hwy 1 shoulder work is completed.

    Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, ADA trail handrail layout, south loop trail, and installing curbs at the upper parking lot area.

  • November 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, ADA trail, south loop trail, and paving and striping at the upper parking lot area.

  • December 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, ADA trail, and south loop trail.

  • January 2025 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, and ADA trail. PG&E is anticipated to begin work on setting new poles and pulling wires.

  • February 2025 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, and ADA trail. PG&E is anticipated to begin work on setting new poles and pulling wires this month.

  • March 2025 - Contractor is continuing their work on interior and exterior paint of CMU Ranger and Restroom buildings, installation of ADA trail handrails, lookout decks, and amphitheater area. PG&E has set new poles and Utilities are preparing to underground their facilities.

  • April 2025 - Contractor is continuing their work on installation of ADA trail handrails, midbluff grading, installation of picnic area, etc. Utility undergrounding work is scheduled to finish by May.

  • May 2025 - Contractor is continuing their work on installation of ADA trail handrails, ranger shed building, landscape planting work, etc. Utility undergrounding work and energization are scheduled to finish in May.

  • June 2025 - Contractor is continuing their work on installation of ADA trail handrails, timber steps, interpretive signs, wayfinding signs, donor sign panels and plaques. Utility undergrounding work and removal of utility poles are scheduled to finish mid-June.

  • July 2025 - Contractor is continuing their work on wayfinding signs, landscape planting, handrail lighting, and pier foundations for wood decks. Installation of ADA trail handrails has been completed. Utility undergrounding work and removal of utility poles are scheduled to finish mid-July.

  • August 2025 - Contractor is continuing their work on wayfinding signs, landscape planting, handrail lighting and guardrail, sidewalk installation, and pier foundations for wood decks. Utility undergrounding work and removal of utility poles are scheduled to finish mid-August.

  • September 2025 - Contractor is continuing their work on ADA pathway stairs, landscape planting, handrail lighting and guardrails. Utility undergrounding work and removal of utility poles are scheduled to finish late-September.

  • October 2025 - Utility undergrounding work was completed with overhead utility poles removed. The Contractor is continuing their work on the upper parking lot area to construct overlook decks and seatwalls. They are also working to install handrail lighting, guardrails, and landscaping along the ADA pathway. Wayfinding signs continue to be installed.

  • November 2025 - The Contractor is continuing their work on the upper parking lot area to construct overlook decks and seatwalls. They are also working to install handrail lighting, guardrails, and landscaping along the ADA pathway.

  • December 2025 - January 2026 - The Contractor is continuing their work on the upper parking lot area to construct overlook decks, sidewalk and curbs. They are also working final erosion control and paving around the site, install guardrails along the ADA pathway, powering ranger shed.

  • February to March 2026 - Contractor working on installing remaining guardrail panels and addressing punchlist items

  • April 2026 Contruction is ongoing for slide repairs. Please refer to this webpage for updates.

  • May 2026 - Punchlist Items are complete. Project closeout.

Tunitas Beach Tunitas Beach March 2023 March 2023 March 2023 March 2023 March 2023 March 2023 March 2023 March 2023 March 2023 March 2023 734863 August 2023 August 2023 700928 August 2023 August 2023 617188 August 2023 August 2023 328857 August 2023 August 2023 144043 August 2023 August 2023 613037 September 2023 September 2023 412842 September 2023 September 2023 145020 September 2023 September 2023 080078 September 2023 September 2023 June 2024 1_Fine grading beach access road June 2024 Fine grading beach access road June 2024 2_Drilling piles for retaining walls on ADA trail June 2024 Drilling piles for retaining walls on ADA trail June 2024 3_Setting I-beams for retaining walls on ADA trail June 2024 Setting I-beams for retaining walls on ADA trail June 2024 4_Pouring concrete for piles on ADA trail June 2024 Pouring concrete for piles on ADA trail June 2024 5_Finishing up installing storm drain facilities June 2024 Finishing up installing storm drain facilities June 2024 6_Retaining walls on ADA trail June 2024 Retaining walls on ADA trail June 2024 7_Start formwork for amphitheater seating June 2024 Start formwork for amphitheater seating June 2024 8_Grading at parking lot area June 2024 Grading at parking lot area Tunitas Creek Beach Impr July 2024 Restroom Building Pad July 2024 Restroom Building Pad Tunitas Creek Beach Impr July 2024 Amphitheater Seating July 2024 Amphitheater Seating Tunitas Creek Beach Impr July 2024 Grading ADA Trail July 2024 Grading ADA Trail Tunitas Beach 1st set of amphitheater seating August 2024 August 2024 Amphitheater Seating Tunitas Beach  CMU Walls being constructed on Ranger Shed August 2024 August 2024 CMU Walls Tunitas Beach Construction of trail steps August 2024 August 2024 Trail Steps Tunitas Beach CMU Ranger Building September 2024 September 2024 CMU Ranger Building Tunitas Beach CMU Restroom Building September 2024 September 2024 CMU Restroom Building Tunitas Beach Upper Parking Lot Concrete Curb September 2024 September 2024 Upper Parking Lot Concrete Curb Tunitas Beach EV Charger Installation in Upper Parking Lot September 2024 September 2024 EV Charger Installation in Upper Parking Lot Tunitas Beach Amphitheater Wooden Deck September 2024 September 2024 Amphitheater Wooden Deck Tunitas Beach Upper Parking Lot September 2024 September 2024 Upper Parking Lot Tunitas October 2024 backfilling and compacting amphitheater 2 October 2024 backfilling and compacting amphitheater Tunitas October 2024 backfilling and compacting amphitheater October 2024 backfilling and compacting amphitheater Tunitas October 2024 Creating and compacting Southern Loop Trail October 2024 Creating and compacting Southern Loop Trail Tunitas October 2024 Formwork for stairs from ADA trail to Amphitheater October 2024 Formwork for stairs from ADA trail to Amphitheater Tunitas October 2024 installing bollards to protect transformer pad October 2024 installing bollards to protect transformer pad Tunitas October 2024 Restroom and Ranger Shed roofing installation October 2024 Restroom and Ranger Shed roofing installation Tunitas October 2024 striping Hwy 1 (night work) 2 October 2024 striping Hwy 1 (night work) Tunitas October 2024 striping Hwy 1 (night work) October 2024 striping Hwy 1 (night work) Tunitas Creek Beach Parking Lot paved and striped November 2024 November 2024 Parking Lot paved and striped Tunitas Creek Beach Restroom OSB siding being installed November 2024 November 2024 Restroom OSB siding being installed Tunitas Creek Beach Highway 1 paving and striping November 2024 November 2024 Highway 1 paving and striping Tunitas Creek Beach BMP installed at Beach Access Road ahead of rainy weather November 2024 November 2024 BMP installed at Beach Access Road ahead of rainy weather Tunitas Creek Beach ADA Trail - placing steel edging November 2024 November 2024 ADA Trail - placing steel edging Tunitas Creek Beach ADA Trail - installing formwork for staircase landing pad November 2024 November 2024 ADA Trail - installing formwork for staircase landing pad Tunitas Creek Beach ADA Trail - formwork for deck foundation November 2024 November 2024 ADA Trail - formwork for deck foundation December 2024 Concrete walkway poured at amphitheater area - Tunitas Beach December 2024 Concrete walkway poured at amphitheater area December 2024 Installation of ADA Trail steel edging - Tunitas Beach December 2024 Installation of ADA Trail steel edging December 2024 Installation of pedestrian stairs at service road - Tunitas Beach December 2024 Installation of pedestrian stairs at service road December 2024 Installing Class 2 AB on ADA Trail - Tunitas Beach December 2024 Installing Class 2 AB on ADA Trail December 2024 Installation of roofing at Ranger Shed Building - Tunitas Beach December 2024 Installation of roofing at Ranger Shed Building January 2025 Completed Pedestrian Stairs at Beach Access Road -Tunitas Creek January 2025 Completed Pedestrian Stairs at Beach Access Road January 2025 Exterior Wall Install at Ranger Shed -Tunitas Creek January 2025 Exterior Wall Install at Ranger Shed January 2025 LookOut Deck at Amphitheater -Tunitas Creek January 2025 LookOut Deck at Amphitheater February 2025 Tunitas - ADA Pathway February 2025 - ADA Pathway February 2025 Tunitas - Amphitheater Seating Area 2 February 2025 - Amphitheater Seating Area 2 February 2025 Tunitas - Amphitheater Seating Area February 2025 - Amphitheater Seating Area February 2025 Tunitas - Look Out Deck at Amphitheater area February 2025 - Look Out Deck at Amphitheater area February 2025 Tunitas - Ranger Shed Exterior February 2025 - Ranger Shed Exterior March 2025 Tunitas Beach - Exterior of Ranger Shed Painted March 2025 Tunitas Beach - Exterior of Ranger Shed Painted March 2025 Tunitas Beach - Installation of handrailing at ADA path March 2025 Tunitas Beach - Installation of handrailing at ADA path March 2025 Tunitas Beach - Installation of Interpretive Signage Panels March 2025 Tunitas Beach - Installation of Interpretive Signage Panels March 2025 Tunitas Beach - New Utility Pole installed (North) March 2025 Tunitas Beach - New Utility Pole installed (North) March 2025 Tunitas Beach - Preparing Ranger Shed Interior March 2025 Tunitas Beach - Preparing Ranger Shed Interior Tunitas Creek April 2025 Decomposed Granite Installation.JPG April 2025 Decomposed Granite Installation Tunitas Creek April 2025 Southern Access Trail - Cross Culvert Installation April 2025 Southern Access Trail - Cross Culvert Installation Tunitas Beach Improvements Project May 2025 - Grading Work at Midbluff Pathway May 2025 - Grading Work at Midbluff Pathway Tunitas Beach Improvements Project May 2025 - Donor Signage Installation May 2025 - Donor Signage Installation Tunitas Beach Improvements Project May 2025 - Handrail Installation at ADA Pathway May 2025 - Handrail Installation at ADA Pathway Tunitas Beach Improvements Project May 2025 - Log Feature at Midbluff May 2025 - Log Feature at Midbluff June 2025 Tunitas Creek Beach - Handrail Delivery June 2025 - Handrail Delivery June 2025 Tunitas Creek Beach - Handrail Installation June 2025 - Handrail Installation June 2025 - Ranger Shed Interior Finishing work June 2025 - Ranger Shed Interior Finishing work June 2025 - Swing Gate Installation - South end parking lot June 2025 - Swing Gate Installation - South end parking lot June 2025 - Wood steps installation to midbluff - Amphitheater area June 2025 - Wood steps installation to midbluff - Amphitheater area June 2025 - Wooden Seat Bench Installation at midbluff June 2025 - Wooden Seat Bench Installation at midbluff Tunitas Beach July 2025 Amphitheatre Area July 2025 Amphitheatre Area Tunitas Beach July 2025 AT&T Splice Work at Utility Vault July 2025 AT&T Splice Work at Utility Vault Tunitas Beach July 2025 Picnic Benches July 2025 Picnic Benches Tunitas Beach July 2025 Trail with Decomposed Granite July 2025 Trail with Decomposed Granite