December 2025 Construction of EV Charger Footing
December 2025 Curb North Entrance Concrete Install
December 2025 Formwork Curb North Entrance
December 2025 Installing AT&T Conduit to Ranger Station
December 2025 Installing Transformer
December 2025 Upper Parking Lot Deck Construction
December 2025 Upper Parking Lot Decks and Seatwalls
December 2025 Upper Parking Lot Installing Seatwall Backs
December 2025 Upper Parking Lot Sidewalk Concrete Install
December 2025 Wiring Ranger Station
October 2025 - Preparing for construction of overlook deck
October 2025 - Utility pole removal
October 2025 - Utility pole removal
October 2025 - Wayfinding signage
September 2025 - Guardrail Installation ADA Pathway
September 2025 - Handrail Lighting Work
September 2025 - Preparing Handrail for lighting
August 2025 - Transformer Box at Ranger Shed
August 2025 - Signage installation
August 2025 - Signage installation 2
August 2025 - Handrail-Guardrail Installation
August 2025 - Concrete work for sidewalk at upperparking lot area
August 2025 - Concrete finishing for sidewalk
November 2025 Progress - grading & gravel bags placed on Access Rd
November 2025 Progress - Placing Fencing around trees at LoneStar
November 2025 Progress - Receiving plants at LoneStar
November 2025 Progress - deck work
November 2025 Progress - Grading at the top level
November 2025 Progress - Placing seat wall concrete
November 2025 Progress - Landscaping Irrigation
November 2025 Progress - Placing seat wall reinforcing steel top level
Previous Updates
- November 2022 - Preparing for demolition phase of the existing single family home
- December 2022 - JOC Contractor and County negotiate on proposal for demolition work.
- January 2023
- Executed JOC Task Order with Olympos Construction for demolition work.
- Board approves DPW's recommendation to finalize plans and specifications and put the improvements project out to bid.
- February 2023 - 100% design in progress.
- March 2023 - House demolition work completed.
- April 2023 - 100% design complete. Project out to bid on 4/27.
- May 2023 - Open bids on 5/25. Low responsible bidder is Gordon N. Ball, Inc.
- June 2023 – Project was awarded to Gordon N. Ball, Inc. by County of San Mateo Board of Supervisors on June 13, 2023.
- July 2023 - Contract execution. The County and Contractor prepare for forthcoming construction work (Submittal and RFI Review).
- August 2023 - Contractor mobilizes on 8/29.
- September 2023 - Contractor works on clearing and grubbing and construction fencing to secure the site.
- October 2023 - Contractor starts on landslide mitigation area, and clear and grub the south access trail.
- November 2023 - Contractor importing soil and continues working on landslide mitigation work. Started installing storm drainage from Upper Lot to Mid-Bluff area.
- December 2023 - Contractor continues working on landslide mitigation work and installing storm drainage from Upper Lot to Mid-Bluff area. Cleared ADA Pathway.
- January 2024 to March 2024 – Project site is winterized.
- April 2024 - Contractor commences construction activities.
- May 2024 - Contractor working on landslide mitigation, storm drain, beach access road, and ADA trail.
- June 2024 - Contractor is working on the beach access road, finishing installing storm drain facilities, ADA trail and retaining walls, amphitheater area, restroom building pad, and grading the parking lot area.
- July 2024 - Contractor completed work on the beach access road and retaining walls. Work on grading the ADA trail, amphitheater area, restroom and ranger shed building pads, installing a waterline and electrical conduits, and grading the parking lot area are ongoing.
- August 2024 - Contractor continued working on installing joint trench, amphitheater area, wood decks, ranger shed foundation, building foundation, and septic tank. Work on CMU walls, parking lots, bioretention areas, pedestrian stairs, wood decks are ongoing.
- September 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, and installation of bioretention areas, curbs, utility conduits, trail, and grading at the upper parking lot area.
Temporary traffic control measures are in place along Highway 1 shoulder. Highway 1 work is anticipated to be completed by mid to late September.
-
October 2024 - Hwy 1 shoulder work is completed.
Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, ADA trail handrail layout, south loop trail, and installing curbs at the upper parking lot area.
-
November 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, ADA trail, south loop trail, and paving and striping at the upper parking lot area.
-
December 2024 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, ADA trail, and south loop trail.
-
January 2025 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, and ADA trail. PG&E is anticipated to begin work on setting new poles and pulling wires.
-
February 2025 - Contractor is continuing to work on CMU ranger and restroom buildings at the midbluff, construction of the amphitheater area, lookout decks, and ADA trail. PG&E is anticipated to begin work on setting new poles and pulling wires this month.
-
March 2025 - Contractor is continuing their work on interior and exterior paint of CMU Ranger and Restroom buildings, installation of ADA trail handrails, lookout decks, and amphitheater area. PG&E has set new poles and Utilities are preparing to underground their facilities.
-
April 2025 - Contractor is continuing their work on installation of ADA trail handrails, midbluff grading, installation of picnic area, etc. Utility undergrounding work is scheduled to finish by May.
-
May 2025 - Contractor is continuing their work on installation of ADA trail handrails, ranger shed building, landscape planting work, etc. Utility undergrounding work and energization are scheduled to finish in May.
-
June 2025 - Contractor is continuing their work on installation of ADA trail handrails, timber steps, interpretive signs, wayfinding signs, donor sign panels and plaques. Utility undergrounding work and removal of utility poles are scheduled to finish mid-June.
-
July 2025 - Contractor is continuing their work on wayfinding signs, landscape planting, handrail lighting, and pier foundations for wood decks. Installation of ADA trail handrails has been completed. Utility undergrounding work and removal of utility poles are scheduled to finish mid-July.
-
August 2025 - Contractor is continuing their work on wayfinding signs, landscape planting, handrail lighting and guardrail, sidewalk installation, and pier foundations for wood decks. Utility undergrounding work and removal of utility poles are scheduled to finish mid-August.
-
September 2025 - Contractor is continuing their work on ADA pathway stairs, landscape planting, handrail lighting and guardrails. Utility undergrounding work and removal of utility poles are scheduled to finish late-September.
-
October 2025 - Utility undergrounding work was completed with overhead utility poles removed. The Contractor is continuing their work on the upper parking lot area to construct overlook decks and seatwalls. They are also working to install handrail lighting, guardrails, and landscaping along the ADA pathway. Wayfinding signs continue to be installed.
-
November 2025 - The Contractor is continuing their work on the upper parking lot area to construct overlook decks and seatwalls. They are also working to install handrail lighting, guardrails, and landscaping along the ADA pathway.
-
December 2025 - January 2026 - The Contractor is continuing their work on the upper parking lot area to construct overlook decks, sidewalk and curbs. They are also working final erosion control and paving around the site, install guardrails along the ADA pathway, powering ranger shed.
-
February to March 2026 - Contractor working on installing remaining guardrail panels and addressing punchlist items
-
April 2026 Contruction is ongoing for slide repairs. Please refer to this webpage for updates.
-
May 2026 - Punchlist Items are complete. Project closeout.