Project No. P30T1; Project File No. E4995

Location

Tunitas Beach

About the Project

San Mateo County Parks is partnering with Peninsula Open Space Trust (POST) and the Coastal Conservancy to protect environmental resources and promote public safety at Tunitas Creek Beach. With participation from the public, the County will be developing this stunning and rugged section of coastline with proper public facilities and amenities.  Visit the project website for additional information:

Public Works Contact

Anthony Lum
Senior Engineer 
alum@smcgov.org
650-363-4100

Contractor

TBD

Documents

N/A

UPDATES
  • November 2022 - Preparing for demolition phase of the existing single family home
  • December 2022 - JOC Contractor and County negotiate on proposal for demolition work.
  • January 2023
    • Executed JOC Task Order with Olympos Construction for demolition work.
    • Board approves DPW's recommendation to finalize plans and specifications and put the improvements project out to bid.
  • February 2023 - 100% design in progress.
  • March 2023 - House demolition work completed.
  • April 2023 - 100% design complete. Project out to bid on 4/27.
  • May 2023 - Open bids on 5/25. Low responsible bidder is Gordon N. Ball, Inc.
  • June 2023 – Project was awarded to Gordon N. Ball, Inc. by County of San Mateo Board of Supervisors on June 13, 2023.
  • July 2023 - Contract execution. The County and Contractor prepare for forthcoming construction work (Submittal and RFI Review).
  • August 2023 - Contractor mobilizes on 8/29.
  • September 2023 - Contractor works on clearing and grubbing and construction fencing to secure the site.
  • October 2023 - Contractor starts on landslide mitigation area, and clear and grub the south access trail.
  • November 2023 - Contractor importing soil and continues working on landslide mitigation work. Started installing storm drainage from Upper Lot to Mid-Bluff area.
  • December 2023 - Contractor continues working on landslide mitigation work and installing storm drainage from Upper Lot to Mid-Bluff area. Cleared ADA Pathway.
  • January 2024 to March 2024 – Project site is winterized.
  • April 2024 - Contractor commences construction activities.
Tunitas BeachTunitas Beach March 2023March 2023 March 2023March 2023 March 2023March 2023 March 2023March 2023 March 2023March 2023 734863 August 2023August 2023 700928 August 2023August 2023 617188 August 2023August 2023 328857 August 2023August 2023 144043 August 2023August 2023 613037 September 2023September 2023 412842 September 2023September 2023 145020 September 2023September 2023 080078 September 2023September 2023