November 2025

Grading work complete. Contractor working on asphalt paving.

September to October 2025

Contractor is continuing with earthwork and site grading.

August 2025

Construction began in early August.

June to July 2025:

Construction is anticipated to start in early July.

May 2025:

Construction to begin pending building permit approval.

April 2025:

Notice to Proceed issued to JOC contractor. Construction to begin in late April/early May.

March 2025:

Design is complete and construction to expected to start in April.


Location

555 Guadalupe Canyon Parkway, Brisbane, CA 94005

About the Project

Park improvements include new ADA accessible picnic sites, asphalt pedestrian walkway replacement, a new ADA restroom facility, and various improvements. Visit the project website for additional information: https://www.smcgov.org/parks/san-bruno-mountain-day-use-improvement

Contractor

Half Moon Bay Grading & Paving

Public Works Contact

Alex Zhang
Senior Civil Engineer
azhang@smcgov.org
650-363-4100

All Projects