Construction Schedule
August 2025 - March 2026
Project Updates
October 2025
The contractor completed installation of all new pipe. They are completing compaction testing with pressure testing and disinfection to follow. Other activities include vault base installation and fire hydrant pad work.
For additional information, please visit https://www.smcgov.org/ceo/smcpescaderoconnect
Project No. PC027; Project File No. 5104
Locations
Pescadero Creek Road between Stage Road and Cloverdale Road
Cloverdale Road between Pescadero Creek Road and Butano Cutoff
Butano Cutoff between Cloverdale Road and Pescadero High School
About the Project
The project will extend CSA 11 water lines to serve Pescadero Middle/High School and the future County Fire Station No. 59. Project includes installing approximately 1.27 miles of 6-inch PVC water main and 7 fire hydrants between Pescadero Middle/High School and the existing CSA 11 water main at Pescadero Creek Road and Stage Road.
Public Works Contact
Leo Chow
Senior Civil Engineer
lchow@smcgov.org
(650) 363-4100
Contractor
GradeTech Inc.