Project No. RW941; Project File No. E5085
Location
El Granada
About the Project
Work will consist of placing a storm drain system on Ferdinand Ave to improve drainage.
Public Works Contact
Wency Ng
Senior Engineer
wng@smcgov.org
650-363-4100
Contractor
TBD
Updates
- November 2023 - Potholing for utilities was performed.
- December 2023 - Received pothole report to implement in design plans.
- January 2024 – Compiled and field verified utility information.
- February/March 2024 - 30% design phase.
- April to July 2024 – 65% design phase.
- August to September 2024 - The 75% plans, specifications and estimate are currently in development.
- October to December 2024 - The 75% plans, specifications and estimate are under review. Targeting completion of 90% plans, specifications and estimate on November 2024.
- January to March 2025 - 90% plans under review.
- April 2025 - 100% plans in design and target to adopt plans by April 2025.