Project No. RW941; Project File No. E5085
Location
El Granada
About the Project
Work will consist of placing a storm drain system on Ferdinand Ave to improve drainage.
Public Works Contact
Wency Ng
Senior Engineer
wng@smcgov.org
650-363-4100
Contractor
TBD
Updates
- November 2023 - Potholing for utilities was performed.
- December 2023 - Received pothole report to implement in design plans.
- January 2024 – Compiled and field verified utility information.
- February/March 2024 - 30% design phase.
- April to June 2024 – 65% design phase.