San Clemente Road August 2025

August 2025 - Existing Conditions

San Clemente Road Culvert Storm Drain Schematic

San Clemente Road Culvert Storm Drain Schematic

Project Updates

January 2026

Project complete. Notice of Completion being filed.

November 2025 to December 2025

Project substantially complete. Project in close out phase.

September to October 2025

Construction to start mid-September with completion in early November.

August 2025

Finalizing Job Order. Contractor to begin construction once contract is executed.


Project No. RW939; Project File No. E5120

Location

254 San Clemente Road (El Granada)

About the Project

The San Clemente Road Culvert Lining Project includes the repair and lining of existing storm drain pipes and restoration of roadway and disturbed easement areas to existing conditions.

Public Works Contact

Alex Zhang
Senior Engineer 
azhang@smcgov.org
650-363-4100

Contractor

SBAY Construction Inc.