August 2025 - Existing Conditions
San Clemente Road Culvert Storm Drain Schematic
Project Updates
January 2026
Project complete. Notice of Completion being filed.
November 2025 to December 2025
Project substantially complete. Project in close out phase.
September to October 2025
Construction to start mid-September with completion in early November.
August 2025
Finalizing Job Order. Contractor to begin construction once contract is executed.
Project No. RW939; Project File No. E5120
Location
254 San Clemente Road (El Granada)
About the Project
The San Clemente Road Culvert Lining Project includes the repair and lining of existing storm drain pipes and restoration of roadway and disturbed easement areas to existing conditions.
Public Works Contact
Alex Zhang
Senior Engineer
azhang@smcgov.org
650-363-4100
Contractor
SBAY Construction Inc.