Project No. SF030; Project File No. E5099
Location
Fair Oaks Sewer Maintenance District, Woodside
About the Project
The project will rehabilitate approximately 1.4 miles of 6-inch pipe along Redwood Creek. It starts north of Mision Trail Road Cul de sac near Interstate 280 and runs southeast along Redwood Creek to Otis Avenue. It restarts again across interstate 280, along same Redwood Creek to Oak Haven Way in unincorporated San Mateo County in the Town of Woodside.
Public Works Contact
America Sanchez
Associate Engineer
acsanchez@smcgov.org
650-363-4100
Design Consultant
BKF Engineers
Contractor
TBD
Updates
-
Feb 2026 – Television inspection of existing pipes 50%