Tunitas Creek Slide Repair Installation of Soil Nails - Pinned Mesh System April 2026.jpg

Installation of Soil Nails - Pinned Mesh System April 2026

Tunitas Creek Slide Repair Installation of Soil Nails - Shotcrete Wall April 2026.JPG

Installation of Soil Nails - Shotcrete Wall April 2026

Tunitas Creek Slide Repair Pinned Mesh System April 2026.JPG

Pinned Mesh System April 2026

Tunitas Creek Slide Repair Shotcrete Wall April 2026.JPG

Shotcrete Wall April 2026

Tunitas Creek Slide Repair April 2026 Drill Test Slide No. 1

April 2026 Drill Test

Tunitas Creek Slide Repair April 2026 Drill Test Slide No. 2

April 2026 Drill Test

Tunitas Creek Slide Repair April 2026 Soil Nail Installation (2) Slide No. 2

April 2026 Soil Nail Installation

Tunitas Creek Slide Repair April 2026 Soil Nail Installation Slide No. 2

April 2026 Soil Nail Installation

Tunitas Creek Slide Repair April 2026 Spider Excavator

April 2026 Spider Excavation Efforts

Previous Project Updates

May 2026

The soil nail pinned mesh system and the shotcrete wall have been completed. The contractor is currently working to install cable rail fencing adjacent to the shotcrete wall, regrade and resurface the top of the slope failure areas with gravel, and repave the access road leading from the parking lot to the slope failure areas.

April 2026

Construction efforts have commenced for this Project. The contractor is currently regrading the slope failure areas in preparation for the installation of a soil nail pinned mesh system and a shotcrete retaining wall.


Project No. P30T1; Project File No. E4995

Location

Tunitas Beach

About the Project

The Tunitas Creek Beach Slide Repair Project includes slope failure stabilization efforts to address two slope failures that occured along the edge of the access road at Tunitas Creek Beach, which leads down to the beach. Stabilization efforts include the installation of a soil nail pinned mesh system and a shotcrete retaining wall with a cable rail fencing. The project also includes the regrading of the access road to improve drainage, as well as the paving of the access road leading up to the parking lot area.

Public Works Contact

Alex Zhang
Senior Engineer 
azhang@smcgov.org
650-363-4100

Contractor

Granite Rock Company

All Projects