All Projects

Project No. RH901; Project File No. E5060 

Location

Ticonderoga Retaining Wall on Ticonderoga Drive, San Mateo, CA

About the Project

The Ticonderoga Retaining Wall includes reinforcing the Ticonderoga Retaining Wall with a cost effective geotechnical solution, including the use of soil nails or light weight structural fill material. In addition to reinforing the wall, portions of affected concrete sidewalk and asphalt road will be repaired.

Public Works Contact

Monika Raman
Senior Civil Engineer
mraman@smcgov.org
650-363-4100

Contractor

TBD

UPDATES
  • February to March 2025 - County is reviewing 100% plans, specifications and estimates. Progressing to final plans and specifications in April.
  • April 2025 - Project out to bid as of April 10, 2025 and scheduled bid opening on May 1, 2025 @ 2:30pm.

  • May 2025 - 

    • Project Plans and Specifications were finalized and advertized for bids.

    • Bids will be opened on May 1st

  • June 2025 - Project has been awarded to Granite Rock Company and is anticipated to start in late June or early July.

  • July to August 2025 - Project has been awarded to Granite Rock Company and is now anticipated to start in Fall of 2025.

  • September 2025:

Anticipated Construction Schedule

  • September 15, 2025,  thru December 29, 2025

Please note: The schedule is subject to change depending on weather, field conditions, or other unforeseen factors.
Traffic Impacts
During construction, the County anticipates lane closures, sidewalk closures and increased traffic congestion. Travel through the area may be slower than usual, and significant delays are expected. We encourage residents and commuters to plan ahead and allow extra time for travel through the affected areas.
Work Schedule
Construction work will typically occur Monday through Friday, from 8:00 a.m. to 5:00 p.m. Traffic control measures, including signage and flaggers, will be in place to guide drivers safely through or around work zones. Detour signage will be installed as necessary to maintain safe and efficient traffic flow.
The Department of Public Works will share updates and information throughout the construction period. 
Thank you for your patience and cooperation as we complete this roadway improvement project.

Location Map Location Map E5060_VICINITY_MAP Vicinity Map TiconderogaRetainingWallImprovementSiteView Site View