June 2025 Existing Parking Lot Condition

June 2025 Existing Parking Lot Condition

June 2025 Existing Parking Lot Condition

June 2025 Existing Parking Lot Condition

June 2025 Existing Parking Lot Condition

June 2025 Existing Parking Lot Condition

Project Updates

January 2026 - Development of 90% design in progress.

November to December 2025 - Development of 90% design in progress.

October 2025 - Development of 90% design in progress.

September 2025 - Development of 90% design in progress.

August 2025 - Development of 90% design in progress.

July 2025 - Development of 90% design in progress.

June 2025 - The Department has resumed the development of the 100% design of the Project.

June 2023 - Project on hold.

February 2023100% design in progress.

January 2023 – 90% design complete.

December 2022 - 60% complete.


Project No. P29Y1; Project File No. E5074

Location

Junipero Serra Park, 1801 Crystal Springs Rd, San Bruno, CA 94066

About the Project

The project includes pavement throughout the park.

Public Works Contact

Alex Zhang
Senior Engineer
azhang@smcgov.org
(650) 363-4100

Contractor

TBD

All Projects