May 2026
Bids were opened on April 29, 2026. The Project is anticipated to be awarded to C.R. Contracting, LLC on the June 9, 2026 Board of Supervisors Meeting. County is working on securing Federal Aviation Administration (FAA) grant funding for the Project.
April 2026
100% project plans and specifications have been completed. The Project is anticipated to be advertised for bids in April 2026.
February to March 2026
Design plans and specifications are currently in development.
January 2026
90% Plans, Specifications, and Estimates are being developed.
Project No. AH040; Project File No. E5140
Location
Half Moon Bay Airport
About the Project
The scope of work for the Half Moon Bay Airport Taxiway Pavement Rehabilitation Project includes, but is not limited to, the pavement crack sealing and seal coat application for Runway Taxiways A, B, and D, as well as the restriping of all newly sealed areas in accordance with the latest FAA specifications.
Public Works Contact
Alex Zhang
Senior Engineer
azhang@smcgov.org
650-363-4100
Contractor
TBD