April 2026
65% Design package review
February to March 2026
65% Plans and Specs in development
January 2026
Design plans and specifications are currently in development.
September to December 2025
Development of 65% design in progress.
May to August 2025
Preliminary Plans being developed
Location
Alpine Road at Rodgers Gulch (La Honda)
About the Project
This project involves replacing a deteriorated culvert pipe with a new larger culvert pipe. Fish passage design is also included in this work.