February 2026 - Installed Generator
Location and Vicinity Map
August 2025 - New Meter & Metal Building
August 2025 - Airfield Lighting Control Panels
July 2025 Metal Framing
July 2025 Installation of New Fence
July 2025 Metal Building
May 2025 - Compaction Efforts - Footing
May 2025 - Excavation Efforts - Footing
April 2025 Utility Work
Updates
February 2026
Generator has been installed and is expected to be commissioned after testing procedures have been completed.
Project No. AH035 County File Number. E5079
Location
Half Moon Bay Airport
About the Project
The electrical systems serving the airfield lighting at the Half Moon Bay Airport require replacement due to their deterioration, as most of these systems have been in place since the original date of construction of the Airport in 1942. The Half Moon Bay Airport Electrical Vault & Generator Project includes the installation of a new electrical vault to replace the existing electrical vault serving the airfield lighting systems, as well as a new diesel-powered generator to supply the airfield lighting systems with power for a minimum of 24 hours, in the event of electrical power outages. Back up power for the airfield lighting systems will improve the Airport’s electrical resiliency and usability during power outages on the coast.
Public Works Contact
Alex Zhang
Senior Engineer
azhang@smcgov.org
(650) 363-4100
Contractor
Anderson Pacific Engineering Construction, Inc.