All Projects

Project No. P30Y1; Project File No. E4948

Location

Coyote Point Park (1701 Coyote Point Drive, San Mateo, CA 94401)

About the Project

The Coyote Point Eastern Promenade Rejuvenation Project includes reconstruction of the eastern promenade and parking lots, a new beach area with flood protection features, and installation of a new restroom facility.

Public Works Contact

Anthony Lum
Senior Engineer 
alum@smcgov.org
650-363-4100

Contractor

Interstate Grading and Paving, Inc.

UPDATES
  • March 2022 - Percent of Time Elapsed 81%, Percent of Contract Complete 85%
  • April 2022 – Percent of Time Elapsed 81%, Percent of Contract Complete 96.2%, Park open to the public on 4/22/22 
  • May 2022 - Percent of Time Elapsed 90.83%, Percent of Contract Complete 98.28%, Contract items completed on 5/5/2022; Notice of Completion filed
  • June 2022 - Project closing process: As-built plans being prepared
Upper parking lot area

Upper parking lot area

Promenade and beach area

Promenade and beach area

New shower facilities

New shower facilities

Bioswale planting in lower parking lot

Bioswale planting in lower parking lot

Paving of promenade walking trail

Paving of promenade walking trail

Bike racks, new restroom, promenade walking trail

Bike racks, new restroom, promenade walking trail

View from upper parking lot area overlooking the promenade and beach

View from upper parking lot area overlooking the promenade and beach

New promenade and seatwalls adjacent to new beach

New promenade and seatwalls adjacent to new beach