All Projects

Project No. RW942; Project File No. E5056 

Location

Bay Road from 5th Avenue to 8th Avenue, Redwood City

About the Project

The project’s preliminary design consists of the installation of storm water main line along Bay Road and additional drainage facilities at the intersection of 6th, 7th, and 8th Avenue.

Public Works Contact

Carter Choi
Senior Engineer
cchoi@smcgov.org
650-363-4100

Contractor

TBD

UPDATES
  • June 2022- 30% design complete.
  • March 2023 – 60% design complete.
  • April 2024 – Potholing Activity scheduled for the week of April 8 to confirmed proposed pipe alignment.
BayRdLocationMapLocation Map BayRdVicinityMapVicinity Map