November 2025 Asphalt Concrete Conform - 3rd Ave
November 2025 Cat Track Striping
November 2025 Crack Sealing
November 2025 Crack Sealing
November 2025 Demo Ramp - Dumbarton Ave
November 2025 Microsurfacing
November 2025 Microsurfacing
November 2025 Pavement Repairs - 2nd Ave
November 2025 Pavement Repairs - 2nd Ave
November 2025 Pavement Repairs - 2nd Ave
November 2025 Ramp Formwork - Westmoreland Ave
Project Updates
December 2025
Project completed and is in closeout phase.
November 2025
Contractor completes ADA curb ramps, pavement repairs, and microsurfacing work. Final striping to occur early November.
Anticipated Construction Schedule
- September 15, 2025 through November 13, 2025
Please note: The schedule is subject to change depending on weather, field conditions, or other unforeseen factors.
Traffic Impacts
During construction, the County anticipates lane closures, sidewalk closures and increased traffic congestion. Travel through the area may be slower than usual, and significant delays are expected. We encourage residents and commuters to plan ahead and allow extra time for travel through the affected areas.
Work Schedule
Construction work will typically occur Monday through Friday, from 8:00 a.m. to 5:00 p.m., with some work on weekend when necessary. Traffic control measures, including signage and flaggers, will be in place to guide drivers safely through or around work zones. Detour signage will be installed as necessary to maintain safe and efficient traffic flow.
The Department of Public Works will share updates and information throughout the construction period.
Thank you for your patience and cooperation as we complete this roadway improvement project.
October 2025
The contractor continues to work on various ADA curb ramps and pavement repairs.
Microsurfacing work is anticipated to begin in late October, followed by striping. Advance notice will be provided before the start of microsurfacing.
September 2025
Contractor continues to work on various ADA curb ramps, and pavement repairs. Microsurfacing and striping work is forthcoming.
August 2025
Contract to be awarded to Golden Bay Construction, Inc. at the August 12th Board Meeting.
July 2025
100% Project Plans and Specifications completed. Project is out to bid. Bid Opening Date is set for Thursday, July 24 at 2:30 PM.
June 2025
90% Project Plans and Specifications development
May 2025
60% Design Development
April 2025:
Field work has been completed. 60% Project plans and specifications being developed
March 2025:
Some field work has been completed. 30% Design package being developed.
Location
North Fair Oaks Area
About the Project
This project involves ADA curb ramp replacement, pavement repairs, micro-surfacing, and pavement striping.
Public Works Contact
Monika Raman
Senior Civil Engineer
mraman@smcgov.org
650-363-4100
Contractor
TBD
October 2025 - ADA Curb Ramp - Concrete Pour
October 2025 - ADA Curb Ramp - Formwork 2
October 2025 - ADA Curb Ramp - Trucated Dome Installed and finishing
October 2025 - Curb Extension - Bulb Out
October 2025 - Pavement Repairs 2nd Ave
October 2025 - Pavement Repairs Dumbarton Ave
October 2025 - Pavement Repairs on Westmoreland Ave
October 2025 - Pavement Repairs on Westmoreland Ave
Location Map
March 2025 Progress
March 2025 Progress