November 2026 - Completed Crosswalk Striping
November 2026 - Completed STOP bar and legend striping
November 2026 - Striping Application Work
October 2026 - Completed Microsurface
October 2026 - Microsurfacing Work
October 2026 - Microsurfacing Work
October 2026 - Striping Layout
October 2026 - Striping Layout
September 2026 - Pavement Repair Asphalt Concrete Application
September 2026 - Pavement Repair Compaction
September 2026 - Pavement Repair Excavation
Project Updates
November 2026
Pavement striping and markings are anticipated to be completed. A final project walkthrough will be conducted to identify and document any outstanding punch list items.
Project No. RW624; Project File No. E5141
Location
Montara and Miramar Areas
About the Project
The work to be done consists, in general, of performing pavement repairs, placing micro-surfacing on various roads in the Montara and Miramar areas in the unincorporated areas of San Mateo County. It also includes replacement of traffic striping, pavement repairs, and pavement marking.