October 2026 - Completed Microsurface
October 2026 - Microsurfacing Work
October 2026 - Microsurfacing Work
October 2026 - Striping Layout
October 2026 - Striping Layout
September 2026 - Pavement Repair Asphalt Concrete Application
September 2026 - Pavement Repair Compaction
September 2026 - Pavement Repair Excavation
Project Updates
October 2026
Contractor has completed pavement repair work and microsurfacing work. Contractor is anticipated to perform pavement striping and markings work.
Project No. RW624; Project File No. E5141
Location
Montara and Miramar Areas
About the Project
The work to be done consists, in general, of performing pavement repairs, placing micro-surfacing on various roads in the Montara and Miramar areas in the unincorporated areas of San Mateo County. It also includes replacement of traffic striping, pavement repairs, and pavement marking.
Public Works Contact
Alex Zhang
Senior Engineer
azhang@smcgov.org
650-363-4100
Contractor
VSS International, Inc.