All Projects

Project No. RW302; Project File No. E5080

Location

West Menlo Park, Ladera, Alpine Road (Ladera), Middlefield Road (between 5th and 8th)

About the Project

The 2023-2024 ADA Ramp Program will evaluate and replace ADA ramps prior to construction of the 2023 and 2024 Pavement Preservation Projects.

Public Works Contact

Alex Zhang
Senior Engineer 
azhang@smcgov.org
650-363-4100

Contractor

John Boylan Engineering, Inc.

UPDATES
  • November 2022 - Start of project development and design. Develop GIS Application to collect data.
  • January 2023 - Conduct desktop/preliminary review of ramps based off of Road Surfacing Projects Lists.
  • July 2023 - Finalizing list of ramps to be updated.
  • December 2023 - Finalized Ramp List.
  • March 2024 - Research and refine ramp replacement criteria.
  • April 2024 - 60% Plans, Specifications, and Estimates in Development.
  • May 2024 - 60% PSE Review. 90% PSE Development.
  • June 2024 - 90% PSE Development.
  • July 2024 - Continue 90% PSE Development.
  • August 2024 - Design to be finalized and advertised for bids in August 2024.
  • September 2024 - Bid Opening took place on August 29, 2024. John Boylan Engineering, Inc. was the lowest responsible bidder. The project will be awarded on September 10, 2024.
  • October 2024 - Construction is anticipated to begin in October.
  • November 2024 - Construction On-going. Reconstruction of 11 of 39 ramps have been completed.
  • December 2024 - Construction On-going. Reconstruction of 38 of 43 ramps have been completed.
  • January 2025 - Construction of all ramps is complete. Contractor to address punchlist items.
  • February 2025 - Construction complete. Project closeout.
CALC @ Vasilakos Ct 2 View Image ADA Ramp Concrete finishing at Wendy Wy & Valpariso a November 2024 November 2024 ADA Ramp Concrete finishing at Wendy Wy & Valpariso ADA Ramp Concrete finishing at Wendy Wy & Valpariso b November 2024 November 2024 Concrete finishing at Wendy Wy & Valpariso ADA Ramp Concrete pour at Wendy Wy & Valpariso November 2024 November 2024 Concrete pour at Wendy Wy & Valpariso ADA Ramp Demo and formwork at Lucky Ave & Avy Ave November 2024 November 2024 Demo and formwork at Lucky Ave & Avy Ave December 2024 Demo Ramp at Woodland School Exit 2023 ADA Ramp Program December 2024 Demo Ramp at Woodland School Exit December 2024 Finish Concrete at Woodland School Entrance 2023 ADA Ramp Program December 2024 Finish Concrete at Woodland School Entrance December 2024 Pour Ramp at Woodland School Entrance 2023 ADA Ramp Program December 2024 Pour Ramp at Woodland School Entrance