Quarry Park Pump Track Project
Pumptrack location


About This Project

In the process of developing the Quarry Park Master Plan a desire was identified to have a community pump track installed at Quarry Park. San Mateo County Parks, community members, and our hired contracor, Gates + Associates, have collaborated to develop a design concept. The bike community has been surveyed about desirable pump track features and Gates + Associates, with the input of a focus group, provided design alternatives. The preferred concept was approved by the Parks Commission on July 14, 2021.

What is a pump track? A pump track is a circuit of rollers, banked turns and features designed to be ridden completely by riders "pumping"—generating momentum by up and down body movements—instead of pedaling or pushing. A pump track is not a jump track.

Quarry Park Pump Track Preferred Concept

Workshop Presentation - November 4, 2020

Next Steps

Steps to select a contractor to build the Quarry Park Pump track are in motion. Designs are complete, permits have been obtained, and the call for construction bids will be posted in January 2022.

While the department had scheduled site grading to begin mid-September, the need to complete the first phase of Quarry Park’s fuel reduction project near the meadow took precedence and ensures no conflict between fuel reduction work and pump track construction moving forward. Construction is expected to begin mid-to-late spring 2022.

 

  • February 2022
    Contract awarded to construction contractor
  • May-June 2022
    Construction of Pump Track
  • Late June 2022
    Construction ends
 

Quarry Park Pump Track Email List

Keep up to date on this project by joining the Quarry Park Pump Track Email List. Subscribe

Updates


Thursday, June 30, 2022

Quarry Park Pump Track Opening July 16

Construction of the Quarry Park Pump Track is almost complete and finishing touches are in progress in preparation for opening day on Saturday, July 16 at 10 a.m. Learn more


Thursday, May 5, 2022

Quarry Park Bike Pump Track Construction, May 9 – June 30

Construction of the Quarry Park Pump Track has begun. Visitors can help this project be completed on time by staying out the fenced project site. Learn more


Thursday, March 24, 2022

Contractor Selected for Quarry Park Pump Track Project

By approval of the Board of Supervisors at their March 22 meeting, American Ramp Company has been selected to construct the pump track at Quarry Park. A construction timeline will be posted to this project website soon. Learn more


Monday, January 10, 2022

Request for Proposals (RFP) for the Quarry Park Pump Track Installation

San Mateo County Parks has solicited a Request for Proposals (RFP) to install the pump track. Learn more


Wednesday, July 14, 2021

Pump Track Approved by Planning Commission

At their July 14 hearing, the San Mateo County Planning Commission took comment and approved, 4 to 1, the plan for a pump track at Quarry Park.


Thursday, January 28, 2021

Pump Track Presentation to Parks Commission

On Thursday, Feburary 4, the Quarry Park Pump Track Preferred Concept will be presented to the Parks Commission.


Tuesday, December 22, 2020

Pump Track Preferred Concept

Input gathered during community meetings and a survey conducted in November have informed development of the preferred concept for the pump track at Quarry Park. The preferred concept will be presented to the Parks Commission and Board of Supervisors this winter as well as Granada Community Services District.

View the Pump Track Preferred Concept


Thursday, November 5, 2020

Pump Track Survey

Now through November 20, state your preferences for the new Quarry Park pump track by taking the Pump Track Survey

Pump Track Virtual Workshop, Nov 4

On Wednesday, November 4th, members of the community join us in a virtual workshop for the design of a new pump track at Quarry Park.