May 5, 2022
  • Construction of the Quarry Park Pump Track has begun with positioning of equipment. Fencing to preserve the safety of the work area will be installed beginning the week of May 9. 

    Visitors can help this project be completed on time by staying out the fenced project site. Please be aware that trucks will be moving in and out the park during construction. 

    Project Timeline

    • May 9: Rough grading begins
    • May 25: Riding feature construction begins
    • June 30: Construction complete